Skip to content

A town square for an unsquare town

redbankgreen

Standing for the vitality of Red Bank, its community, and the fun we have together.

RUMSON: UTILITIES TO GO BELOW RIVER

rumson-sb-gas-h20-013017-3-500x375-5827392Natural gas and water supply lines are to be tunneled beneath the Shrewsbury River between Rumson Road in Rumson, above, and Sea Bright. (Photo by John T. Ward. Click to enlarge)

By JOHN T. WARD

hot-topic_03-220x138-2130637Residents of Rumson and Sea Bright may see an unusual construction project as early as next month, when two utility companies run new service lines connecting the towns 25 feet below the floor of the Shrewsbury River.

Municipal and utility officials said they expect minimal disruption to traffic during the monthlong project, when New Jersey Natural Gas and New Jersey-American Water plan to drill beneath the river from Sea Bright to Rumson and then pull about a quarter-mile of piping across the span.

The new gas and water lines line, shown in yellow, will run through openings to be drilled from the parking lot of the Sea Bright Beach Club to Rumson. The green line indicates the location of the existing water supply, which runs along the riverbed and will be abandoned, officials said. (Photo by John T. Ward. Click to enlarge)

rumson-sea-bright-gas-water-map-013117-220x163-3783961According to officials of the two companies, contractor J.F. Kiley Services, working from the parking lot of the Sea Bright Beach Club, will use horizontal directional drilling technology to bore down and then under Ocean Avenue and the river to the eastern end of Rumson Road.

Though it may call to mind fracking technology, the drilling technique does not employ any toxic chemicals or generate toxic waste, said gas company spokesman Mike Kinney. “It uses a mud as a lube that’s made of naturally occurring elements that are non-toxic,” he said.

Drilling under rivers and wetlands is “not only common, it’s the DEP’s preferred way of doing this,” Kinney said, referring to the New Jersey Department of Environmental Protection.

For the gas company, the aim of project, which calls for 1,406 feet of 12-inch steel piping, is  to complete a supply circuit “to better mitigate” the impact of service disruptions caused by storms and construction accidents, said Kinney. It’s part of a six-project, $102.5 million system “hardening” approved by the New Jersey Board of Public Utilities two years after Hurricane Sandy caused extensive damage in October, 2012.

As its part of the joint project, the water company plans to spend some $2.5 million to run 1,200 feet of 16-inch diameter high-density polyethylene pipe to replace a concrete pipe that runs along the riverbed from Washington Street in Rumson to River Street in Sea Bright, said water company operations superintendent George Bauer.

The existing line, installed in the 1950s, had to be repaired sometime in the 1990s after was struck by an unmoored barge at low tide, Bauer said. It will be abandoned in place, he said.

Water company officials said the connection will enable continued service during events such as the water main break in Little Silver last July that disrupted service to Rumson.

Each company will have its own sub-river opening, Bauer said.

Pipe segments will be “staged” on the lightly-traveled “old” Rumson Road alongside the Route 520 bridge, where they’ll be welded or fused together shortly before being pulled through the new opening, officials of both companies said.

At no point will homeowners lose driveway access, Rumson Administrator Tom Rogers told redbankgreen via email Monday. Additionally, he said, officials don’t expect road closures to last “more than the time it takes to string out the pipes, assemble them and pull them thru to Sea Bright. The drilling itself, which takes the longest, will not require major closures.”

Sea Bright residents and passersby, meantime, won’t experience any disruption as the construction activity is entirely limited to the beach club parking lot, said Kinney and Bauer.

Still, Mayor John Ekdahl said the companies are under the gun to complete the work before the start of the summer beach season. “We have a short window to do this,” Bauer acknowledged.

Denise Venuti Free, a spokeswoman for the water company, said the project is currently slated to begin on March 7 and be completed by April 21, but that the timetable is dependent on the issuance of permits by the New Jersey Department of Environmental Protection and the Army Corps of Engineers.

According to DEP spokesman Larry Hajna, the gas company applied for three permits last August, and has obtained two, with the third pending. The water company’s permit application was filed in December and is under review, Hajna said. A spokesman for the Army Corps of Engineers said permit applications are under review.

Remember: Nothing makes a Red Bank friend happier than to hear "I saw you on Red Bank Green!"
redbankgreen Classics
Partyline
EDITH BLAKE HEADS FOR 108 YEARS
Belated, we know, but worth honoring regardless: Red Bank's likely oldest resident marks another milestone.
TWO EAGLE MORNING
A pair of bald eagles were in conversation on a branch overlooking the Swimming River in Red Bank Wednesday morning. (photo by Brian Donohue ...
REFLECTIONS ON A GRAY DAY
A pair of chairs placed in the intertidal zone along the shore of the Swimming River sit in the shallows on a grey March morning. (photo by ...
SPRING BUSKIN’ OUT
A busker on Broad Street strums away in the March sunshine Friday. (photo by Brian Donohue)
WHATA BUNCHA BULL SHEET
We thought we at redbankgreen had the pulse of our community, until we read the Asbury Park Press and saw this ad on their site. Apparently ...
NAVESINK SUNRISE
Sunrise over the Navesink River, seen from NJ Transit Coastline train 3320 Monday morning. (Photo by Partyline contributor Karly Swaim)
Stunning Sunrise Views from NJ Transit Train 3320
Sunrise over the Navesink River, taken from NJ Transit Coast Line train 3320 this morning. (Photo by Partyline contributor Karly Swaim) Want ...
BUT FAMILY MEANS NOBODY GETS LEFT BEHIND!
The most famous line from the Disney film “Lilo and Stitch” may be “family means nobody gets left behind.” And three ...
LOCAL MAN WAITING ‘TIL NEXT YEAR AGAIN
We at redbankgreen know there are people who are absolute fanatics of our weekly “Where Have I Seen This” challenge.  But we al ...
FROZEN SNAKE WEATHER
Down among the serpentine turns in the Swimming River, this eastern garter snake was found frozen stiff in the frigid weather. There were no ...
THIS LOT IS GOING TO POT!!
Do NOT hit this monster pothole in Red Bank’s best parking lot for people watching or your weekend plans may go up in smoke. In the backgr ...
DEM GOV HOPEFUL FULOP VISITS RED BANK
110 people braved the ice on Super Bowl Sunday morning to head to Triumph Brewery to hear Steve Fulop’s case for why he should be our ...
REAL BRICKS!
Pardon our nerdiness, but we were excited to see the facade of the long-vacant building at 42 Monmouth being renovated with a facade that ap ...
NAVESINK SUNRISE
Sunrise colors Sunday over the Navesink. Shot from Maple Cove. (photo by Partyline contributor Thomas Doremus)
PET OWNER TO RED BANK: SCREW YOU
(photo and text by Partyline contributor Anna Cruz; headline by redbankgreen) Remember to scoop the poop!  
A HAIR DRYER IN A TREE?
(Photo and text by Partyline contributor Nicole Taetsch) If someone is missing a red hair dryer, it’s hanging from a tree on Oakland S ...
FROM DEEP LEFT FIELD..
(Photo and words by Partyline contributor Peter Cavalier) Shapes, Angles, and Colors: an Artist’s Canvas Where: A frigid Saturday morn ...
SUNSET ICE BOATING
Sunset ice boating Saturday. (photo by Partyline contributor Thomas Doremus)
ICY NAVESINK BLISS
Ice boating is back, baby! (Photo by partyline contributor Boris Kofman)
TEACHERS GET COUNCIL KUDOS
The Mayor and Borough Council honored five teachers from the Red Bank Borough Schools who were selected for the Governor’s Educator of the ...