The closure was required to allow for reconstruction of the intersections on both ends of the spans the Red Bank side is shown above, as seen Tuesday afternoon.
The shutdown was also needed to permit crews to relocate overhead utilities running alongside the old bridge to underneath the new span. That work is still underway, and may require alternating traffic flows Wednesday and Thursday, Red Bank police Chief Darren McConnell tells redbankgreen. (Photos by John T. Ward. Click to enlarge)