RED BANK: JUDGE NIXES POWER LINE PLAN

Homeowners living along the line and other objectors packed a public hearing on the JCP&L proposal held at Brookdale Community College last March. (Photo by John T. Ward. Click to enlarge.)

By JOHN T. WARD

HOT-TOPIC_03Electrical utility JCP&L has failed to prove it needs a to build a controversial 10-mile long, high-voltage electricity transmission line that would end in Red Bank, a judge has ruled.

The decision, handed down Thursday, represents at least an interim victory for a grassroots effort led by homeowners to thwart the proposed $111 million project.

Read More »

RED BANK: POLE DOWNED ON BROAD STREET

A pedestrian suffered minor injuries when she was hit by falling debris as a FedEx truck exiting the Red Bank Post Office caught overhead wires and pulled a utility pole down on Broad Street at about 4:40 p.m. Thursday, according to police Chief Darren McConnell.

Read More »

LINCROFT: RESIDENTS ZAP JCP&L LINE PLAN

Many in the crowd came with signs and wore stickers indicating the distance of their homes from the proposed power line. (Photo by John T. Ward. Click to enlarge)

By JOHN T. WARD

Thwarted from speaking two months ago, hundreds of opponents of a proposed high-voltage electricity transmission line from Aberdeen to Red Bank came electrified with anger Tuesday night.

The occasion was a public comment session at Brookdale Community College on the Jersey Central Power & Light Company proposal, which calls for support poles as tall as 210 feet running for 10 miles along the North Jersey Coast Line railroad, ending at a substation in Red Bank.

Read More »

ON THE GREEN: BECK, KYRILLOS OPPOSE LINE

rb njt 041014A view north along the North Jersey Coast Line from the Red Bank train station. The proposed JCP&L power line would be strong alongside the railroad right-of-way on poles as tall as 140 feet. (Photo by John T. Ward. Click to enlarge.)

By JOHN T. WARD

HOT-TOPIC_03A controversial 10-mile long, high-voltage electricity transmission line that would end in Red Bank is no more welcome today than it was when it was shelved more than two decades ago, two local legislators said Thursday.

State Senators Jen Beck, of Red Bank, and Joe Kyrillos, of Middletown, jointly introduced a trio of resolutions in Trenton aimed at blocking electricity provider JCP&L from building the line.

Read More »

FAIR HAVEN: INVESTORS BANK PLAN STALLS

investors-bank-091316The Investors Bank proposed for River Road would be identical to this branch in Woodbridge, the developer said. (Photo by M&M Realty Partners. Click to enlarge.)

By JOHN T. WARD

HOT-TOPIC_03A proposed drive-thru bank on the site of a former filling station in Fair Haven ran out of gas Tuesday night.

The Investors Bank project encountered continuing objections to a traffic-flow plan that would put two driveways — for an entry and an exit — on River Road, which planning board members said raised child-safety concerns.

Also an issue: the brand-specific look of the one-story building, which called for a shallow glass atrium dome that one resident likened to a “blister.”

Read More »

RUMSON MAN SENTENCED FOR MARKET CRIMES

A Rumson commodities trader who owned and managed a Red Bank firm was sentenced to three years in federal prison last month for market manipulation, the Federal Bureau of Investigation announced Friday.

Michael Coscia, owner of Panther Energy Trading, was convicted in Chicago last November in the first-ever federal prosecution for “spoofing” under the 2010 Dodd-Frank financial reform law, the FBI said.

Read More »

FAIR HAVEN: BANK HEARING DELAYED AGAIN

fh bank plan 051016 1HOT-TOPIC_03For the second time since it began in May, a hearing on a proposed Investors Savings Bank branch on the former site of a Sunoco station on River Road in Fair Haven has been postponed at the applicant’s request. The matter, scheduled for Monday night, is now slated for July 28.

Meantime, the board is expected to continue its review of the town’s Master Plan, among other matters.

For redbankgreen’s prior coverage of the bank plan, click here.  (Photos by John T. Ward. Click to enlarge.)

 

FAIR HAVEN: LUCARELLI BACKS JCP&L PLAN

ben lucarelli 042915 2Fair Haven Mayor Ben Lucarelli says the controversial transmission line may help his town avoid a repeat of the long outage experienced after Hurricane Sandy. (Photo by John T. Ward. Click to enlarge.)

By JOHN T. WARD

HOT-TOPIC_03Fair Haven Mayor Ben Lucarelli stepped onto a political third rail Tuesday, proclaiming his support for a controversial 10-mile long, high-voltage electricity transmission line that would end in Red Bank.

Read More »

RED BANK: COUNCIL TABLES JCP&L STATEMENT

rb train station 062216 3The 10-mile high-capacity power line would run above the Red Bank train station on new, taller pylons and terminate a few blocks south at a power substation, according to JCP&L. (Photo by John T. Ward. Click to enlarge.)

By JOHN T. WARD

HOT-TOPIC_03The Red Bank council tabled a resolution Wednesday night opposing a proposed 10-mile long, high-voltage electricity transmission line that would end in the borough.

Councilman Mark Taylor put the brakes on the measure when he said he hadn’t seen it before the start of the governing body’s semimonthly meeting and wanted a chance to do some research into the issues.

Read More »

LINCROFT: DOUBTS ON JCP&L PLAN REMAIN

JCP&L 060716 2Kyle King, an environmental health consultant to JCP&L, was surrounded by questioners at the event.  (Photo by John T. Ward. Click to enlarge.)

By JOHN T. WARD

HOT-TOPIC_03Plans for a 10-mile long, high-voltage electricity transmission line terminating in Red Bank drew dozens of concerned residents to an information session in Lincroft Tuesday night.

Dubbed the Monmouth County Reliability Project, the 230-kilovolt transmission line is needed to keep pace with demand for electricity, according to Jersey Central Power & Light.

But residents living along its path — the existing New Jersey Transit right-of-way between existing substations in Aberdeen and Red Bank — said they fear it will have harmful health effects and reduce home values.

Read More »

RED BANK: JCP&L REVIVES POWER LINE PLAN

rb bridge ave 041014A view of the North Jersey Coast Line northward from the Red Bank station in 2014. (Photo by John T. Ward. Click to enlarge.)

HOT-TOPIC_03Jersey Central Power & Light is reviving a plan, mothballed 25 years ago, for a high-voltage electricity transmission line to Red Bank, according to a report by NJ.com.

The 230-kilovolt transmission line would run along the existing New Jersey Transit right-of-way between existing substations in Aberdeen and Red Bank. And it’s needed to keep pace with demand for electricity, the company says.

Read More »

FAIR HAVEN: SKEPTICISM OVER BANK PLAN

fh bank plan 051016 1An architectural rendering of the bank, proposed for the former site of a Sunoco station.  (Photos by John T. Ward. Click to enlarge.)

By JOHN T. WARD

fh bank plan 051016 2Like a customer at a balky ATM, a regional bank will have to try again after Fair Haven’s planning board raised numerous objections to a proposed bank branch Tuesday night.

Though the matter didn’t go to a vote, all but one board member cited misgivings about Investors Savings Bank’s plan for a branch on the site of a former River Road filling station.

Read More »

RED BANK: WARNING ON FAKE JCP&L CALLS

AUTHORITIES_RB1Red Bank officials are warning residents of a phone scam making the rounds.

In an alert issued Wednesday, the police said the scammers use methods to trick residents into believing the calls come from electric utility JCP&L.

Read More »

RED BANK: CRUSHING IT DOWNTOWN

RB TRASH 101315
HOT-TOPIC_03
New to the Red Bank business district:
solar-powered trash compactors paired with recycling bins, which RiverCenter executive director Jim Scavone says should help reduce spillage by holding five times the volume of standard containers. They also alert the borough when they’re full, he said.

The bins are or will soon be in four locations, said Scavone: on Broad Street outside Urban Outfitters and Starbucks; on Monmouth Street at the Count Basie Theatre; and outside West Elm on West Front Street. RiverCenter and the borough government splt the cost of the devices, which go for about $6,000 per set, Scavone said. (Photo by John T. Ward. Click to enlarge)

RED BANK: GAS LEAK CAPPED

rb gas leak 081315rb gas leak 081315 2Responding to a gas leak reported shortly before 5 p.m. Thursday at the intersection of Rector Place and West Front Street in Red Bank, a crew from New Jersey Natural Gas Company stopped the leak at 5:44 p.m. Details about the incident were not immediately available. The Red Bank Fire Department also responded.

The intersection is one of two now closed to traffic for reconstruction in conjunction with utility work on the new Hubbard’s Bridge that has detours in place for two-to-three weeks, causing significant traffic delays. (Photos by John T. Ward. Click to enlarge)

FAIR HAVEN: LUCARELLI PUMPS FOR BIKE LANE

ben lucarelli 1 061612Mayor Ben Lucarelli heads to D.C. this week to sharpen his biker-and-pedestrian safety campaign. (Photo by John T. Ward. Click to enlarge)

By JOHN T. WARD

HOT-TOPIC_03Anyone who’s heard Fair Haven Mayor Ben Lucarelli talk about biking safety knows it’s an issue he’s passionate about.

And listening to him talk about the biking-and-walking safety program he’s attending in Washington, D.C., this week, you’d think he was charging down to the capitol on two wheels.

“I would, if I had the time,” Lucarelli told redbankgreen on Tuesday.
Read More »

RED BANK: EV CHARGER SWITCHED ON

rb ev space 121614 1park itAfter a false start involving an enabling ordinance, Red Bank’s first  public charging station for electric vehicles is now legally approved and switched on, borough officials said.

Located outside borough hall at 90 Monmouth Street, the station doubles as a parking space for plugged-in cars, at $2 per hour, juice included. As elsewhere in town, however, the parking fee is waived through December 25. (Photo by Trish Russoniello. Click to enlarge)

 

RED BANK: LOFTS LAND WEST ELM AS TENANT

west elm 120414The furniture retailer will occupy the ground-floor corner at West Front Street and Bridge Avenue, as shown in this rendering. (Click to enlarge)

By JOHN T. WARD

retail churn smallRed Bank’s West Side Lofts project now under construction has landed upscale furniture retailer West Elm as an anchor tenant.

The pending arrival of the store, slated for next August, was at the center of a handful of changes to the massive project the borough zoning board approved Thursday night.

Read More »

RED BANK: GAS LEAK SLOWS THE FLOW

rb traffic 111814rb traffic 111814 2Repair work on a leaking natural gas line on Riverside Avenue in Red Bank had northbound traffic on Route 35 backed up nearly to Waverly Place early Tuesday afternoon as vehicles encountered a one-lane bottleneck just past West Front Street. Both southbound lanes were closed for the length of Riverside, though Middletown police report no significant backups from detours. Red Bank police say they’ve been told the work should be completed by about 4 p.m.

Update, 2:45 p.m.: as seen in the photo at right, traffic is backing up onto Cooper Bridge. (Photo by John T. Ward. Click to enlarge)

RED BANK: EV SPACE? HOLD THAT THOUGHT

RB EV CHARGER 110614 2The public charging station, located outside borough hall, remained under wraps Thursday afternoon. (Photo by John T. Ward. Click to enlarge)

By JOHN T. WARD

park itIt seems somebody at Red Bank borough hall was a little premature in telling redbankgreen that the town’s first and only public electric vehicle charging station would go live Thursday.

Read More »